|
Town Hall
About
Budget 09-10
Budget 10-11
Calendar of Events
Employment
Flood Information
Gallery
Gomez Children Trust Fund
History
Home
Hurricane Information
Links
Maps
Meeting Minutes
New Resident
Information
News
Newsletters
Ordinances/Resolutions
Parks
Town Officials
Town Updates
Volunteering
Building & Zoning
Business/Occupational Licensing
Code
Forms
Maps
New
Building Checklist
Permit Fees
Permit Process
Permit Status
Police Department
About
Employment
Monthly Activity Reports
News
Alerts
ORPD Links
Support Group
| |
Town
Update - May 2005
FDOT & Landscaping Meeting
- The Mayor and Town Manager met with representatives from FDOT and the
Landscaping rep that will be working on the landscaping along
North Ocean Blvd.
We were told that FDOT would begin construction in March 2006 on widening
the road and constructing a swale. We
were assured that any landscaping that was disturbed would be replaced.
The Mayor reminded FDOT that the ROW should be enhanced as per the
original meeting two years ago. We
were assured that the Town would have input as the Construction begins.
Stormwater Drainage Project - South Phase
– On
April 18, 2005
Chaz Equipment Company, Inc. (Chaz) was given the
notice to proceed to start work on the South Phase of the stormwater drainage
project. The contractor (Chaz) has
completed the majority of the clearing of the
Woolbright Road
detention area.
They will be starting to excavate the area and relocate some of the
remaining trees. According to the
agreement with the Contractor the project is to be substantially complete in two
hundred forty eighty (248) days from the notice to proceed date.
Landscaping
– A Classy Cut Property Maintenance Service, Inc. (Classy Cut) has completed
the replanting of the landscaping on
Woolbright Road
that was damaged by
the Hurricanes. Classy Cut has also
completed the installation of additional landscaping in the Town right-of-way
along
Old Ocean Blvd.
adjacent to
Hersey Drive
.
They are now working on repairing the irrigation system on
Ocean Avenue
. The
Town added the mowing of the
Anna Street
right-of-way from A1A
west to the Intracoastal water to Classy Cut’s contract.
State
Revolving Fund Loan – On
April 10, 2005
a disbursement check in the amount of $152,705
for the stormwater drainage improvements was received from the Florida
Department of Environmental Protection (FDEP).
This disbursement request was a result of the loan agreement amendment
which increased the disbursable amounts for the administrative and engineering
allowances. This disbursement was
for the administrative allowance of $16,441 and engineering allowance of
$136,264. On
April 15, 2005
the second disbursement request for the
mechanical equipment for the South Phase of the stormwater drainage improvements
in the amount of $160,141 was submitted to the FDEP.
On
April 22, 2005
the executed change order to the Hudson Avenue
Phase contract for the addition of the
David Lane
and
Adams Road
drainage and roadway improvements was submitted
to the FDEP. This change order was
submitted to the FDEP to add the cost of these improvements to the Town’s
State Revolving Fund Loan. The new
contract amount for the Hudson Avenue Phase will be increased by the change
order in the amount of $199,540. The
new contract amount for this phase including the change order will be
$1,014,741.50.
Hazard
Mitigation Grant Program – FEMA
has made eligible $18,950,316 to
Palm Beach
County
for the Hazard Mitigation Grant Program (HMGP)
as a result of
damages caused by Hurricanes Charley, Frances and Jeanne. This
HMGP provides grant funding to State
and local governments to implement long-term hazard mitigation measures after a
major disaster declaration. The
purpose of the program is to reduce the loss of life and property due to natural
disasters and to enable mitigation measures to be implemented during the
immediate recovery from a disaster. The
projects that are eligible to apply for funding include building acquisition,
elevation, drainage and wind retrofit projects.
On
May 2, 2005
the staff will be submitting HMGP
applications for two (2) projects. The
first mitigation project is for funding for the
hardened construction of the proposed new Town Municipal Building for wind
protection during a hurricane or major storm event.
The second mitigation project is for funding for the
Coconut Lane
drainage wells and improvements. |